In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.
ActivityTaskPredecessorsDurationActivity Cost
ASign ContractNone5 days$5,000
BDesign SurveyA3 days$1,500
CIdentify AudienceA7 days$1,000
DRun SurveyB, C30 days$6,000
EAnalyze ResultsD5 days$3,000
FCreate PresentationE5 days$1,000
GPresent to ClientE, F2 days$3,000