true/false
•
17. Risks are prioritized based on the order they are identified.
•
18. Risks on the critical path should be given higher priority because if the risk occurs, it
would have a greater impact on the schedule than if it was associated with activities on a
path that has a large positive value of total slack.
•
19. A risk assessment matrix is a tool for making a responsible individual responsible for
the risk.
•
20. Risk assessing involves regularly reviewing the risk management matrix throughout
the project.